Client: TMR
- Remove concrete toe planks from lanes
- Reprofile the area with rock, ensuring alignment & stability, before reinstalling planks
- Supply and place 20 tonnes of rock around shoulders of both ramps to reinforce the areas
- Reinstate the toe with additional rock
- Survey riverbed and remove obstructions before mattress installation
- Install Scour Tech fabric formwork mattresses to ensure stable base on both boat ramps
- Ensure mattresses are aligned and positioned correctly
- Fill mattresses with concrete