QAL waste line, Gladstone – Replacement of crossbeams, installation of pilemedic, installation of scour bags
Client: McConnell Dowell
Project Dates: July to November 2021
OVERVIEW
- All remedial works on Areas 6 & 8 of the QAL Waste Line (all sections across mudflats and water).
- Remedial works included installation of solution Pilemedic, replacement of crossbeams (working at heights) and installation of custom scour solution Scour Tech.
- 210 piles remediated (strengthening and protection); 120 structural transverse bracing replacements, 250+ additional structural and durability repairs, 35 Scour Tech grout bags installed
- Provision of plant such as dive equipment, vessels, barges and pontoons
- Detailed interim Progress Report delivered to McConnell Dowell for their Client QAL.
- Reporting, including compliance to ITPs.