Webb Dock & McGraw Wharf, Tasmania – Pile remediation, installation of scour mats
Client: McConnell Dowell
Project Dates: Jan – April 2019
OVERVIEW
- Remediation of 19 piles using Denso Seashield Marine 2000FD, piles averaging 15m in length
- Design, manufacture and install of scour solution, ScourTech
- Shipping schedule of the berth (TOLL Shipping Berth) – night works often required to maintain schedule
- Mobilisation to Burnie, Tasmania from Brisbane
- Provision of plant such as dive equipment, vessels, barges and pontoons
- Daily reporting to Client and adhering to their intensive site safety regime, including CMG’s internal daily reporting requirements
- Total length of all piles was 259m, resulting in the use of 136 jackets