Webb Dock & McGraw Wharf, Tasmania – Pile remediation, installation of scour mats

Client: McConnell Dowell

Project Dates: Jan – April 2019

OVERVIEW

  • Remediation of 19 piles using Denso Seashield Marine 2000FD, piles averaging 15m in length
  • Design, manufacture and install of scour solution, ScourTech
  • Shipping schedule of the berth (TOLL Shipping Berth) – night works often required to maintain schedule
  • Mobilisation to Burnie, Tasmania from Brisbane
  • Provision of plant such as dive equipment, vessels, barges and pontoons
  • Daily reporting to Client and adhering to their intensive site safety regime, including CMG’s internal daily reporting requirements
  • Total length of all piles was 259m, resulting in the use of 136 jackets