Projects

More Projects & Case Studies

Underwater Inspection & Hydrus AUV 3D Mapping | CMG Great Keppel Island

Middle Island Underwater Observatory Inspection Client: DEMEXDate: September 2025 Commercial Marine Group was engaged by

20253D ScanningDEMEXHydrus AUVProjectsUnderwater Inspections
Port North Common User Berth Deconstruction and Removal Works

Client: Brady Marine and Civil | Port of Brisbane Commercial Marine Group was engaged by

Brady Marine & CivilBrisbane PortDecommissioningProjects

Download Our Capability Statements

Brisbane City Council, Brisbane – Gabion repair & installation

BCCMarine Civil ConstructionMarine Scour SolutionsProjects

Client: Brisbane City Council

Brisbane City Council required Commercial Marine Group (CMG) to repair the failing gabions, stabilization of the bank, stop progression of the river wall armor failure.

The scope included:

  • Remove any rubbish with the footprint of the exposed bank
  • Remove the failed gabion baskets and gather any rocks for reuse for repacking of mattresses.
  • Cut-off the bottom four sections of the failing mattresses
  • Remove the Geofabric if damaged
  • Carry out compressibility test according to table 6.1 of S140 document.
  • Trim, level and compact the location where the failed gabion baskets and the mattresses are removed
  • Replace and Reinstall the failed four baskets
  • Rewire and repack the bottom four sections of the mattresses with 4 new sections, reuse the rocks collected from the failed gabion baskets and mattresses if possible.