Client: Georgiou and BMD Joint Venture
- Pre-installation inspection
- Environmental controls (if required)
- Submission of Work Method Statement to The Contractor
- Removal of existing metal framework debris at Pier 3 Pile 2 and Pier 2 piles 6, 7 & 8
- Supply, delivery and unloading of all materials
- Plant and equipment to facilitate the works (such as boats and pontoons)
- Water blasting the surface of the piles at 3500kpa to remove marine growth and ascertain surface condition.
- Installation of FRP pile jacket or form a tube solution and filling of the anulus with grout for 7 x piles with 2m long jackets
- Certification of works