Client: MCM
Project Dates: June-July 2024
- 18 Piles across 3 Piers required remediation
- Clean barnacles off piles with the use of pneumatic underwater chisel. This is required to remove marine growth and any soft surface layer that’s accumulated on the pile.
- Install Pilemedic, Laminate FRP jacket – double wrap
- Hydrovac to excavate sea bed at the pile base prior to sliding the jacket down