Port North Common User Berth Deconstruction and Removal Works

Client: Brady Marine and Civil | Port of Brisbane Commercial Marine Group was engaged by

Brady Marine & CivilBrisbane PortDecommissioningProjects

Download Our Capability Statements

Port North Common User Berth, Brisbane – Dredging, Install Scour Mats

Brady MarineMarine Civil ConstructionMarine Scour SolutionsProjects

Client: Brady Marine

Asset Owner: Ports North

Port North Common User Berth required Fabric Formed grout mattresses to be installed around the intake structure to provide protection against scour.

To be able to achieve this, installation dredging operations were required to remove 220m3 of sediment to achieve the required design RL.

The grout mattresses specified for this project are 400mm thick to provide protection around the piles and intake strainer against scour. Scour Tech has a proprietary product for this application created from Geotextile material. The Fabric Formed Mattresses are custom designed and built to cater for the structure’s needs, providing formwork for pouring concrete within the marine environment

Project Gallery