Urangan Harbour Boat Ramp – Repair & Installation of Scour Tech Mattresses

Client: TMR
Pikenba Wharf (SIMS Metal), Brisbane – Pile remediation using the Jack Up pile method and install scour protection (scour bags) at the base of the piles

Client: Brady Marine & CivilProject Dates: September 2023 – April 2024 OVERVIEW
Ichthys LNG MOF Wharf Cofferdam, NT – Pile inspection, ROV survey, Geotechnical investigation

Client: INPEX Ichthys LNGProject Dates: 2022 – on going OVERVIEW
Port North Common User Berth, Brisbane – Dredging, Install Scour Mats

Client: Brady Marine Asset Owner: Ports North Port North Common User Berth required Fabric Formed grout mattresses to be installed around the intake structure to provide protection against scour. To be able to achieve this, installation dredging operations were required to remove 220m3 of sediment to achieve the required design RL. The grout mattresses specified […]
Brisbane City Council, Brisbane – Gabion repair & installation

Client: Brisbane City Council Brisbane City Council required Commercial Marine Group (CMG) to repair the failing gabions, stabilization of the bank, stop progression of the river wall armor failure. The scope included:
Fitzroy River Barrage, Rockhampton – Install scour mats

Client: PensarAsset Owner: Sunwater As part of the works, a portion of the existing weir requires to be cut to allow the placement of the fishway exit. At the time of Issuing for Construction, the excavation of the existing embankment at the exit was not considered. It is now understood that to complete the fishway […]
Hamilton Siphon Bypass Pipeline, Brisbane – Install pipeline and scour mats

Client: Fulton HoganAsset Owner: Urban Utilities The Hamilton Siphon Bypass Pipeline C is an subsea pipeline across the Brisbane River for the transfer of sewage. The subsea pipeline design and construction methodology is unique for the specific constraints and limitations of the Brisbane river. Close collaboration enabled the team to deliver the project in 11months […]
Ampol Products Wharf, Brisbane – Install Jack up piles & remove piles

Client: Brady MarineProject Dates: 2023-2024 OVERVIEW The innovative pile jack up repair provides a solution to underwater piles needing an extension of design life. The marine borer erodes the piles at seabed level and far more rapidly than rest of the structure, meaning the useful life of the facility is compromised. The team uses a combination […]
Port Kembla Gas Terminal, NSW – Quay wall repairs, welding, inspections, dredging, concrete pumping, install scour mats and cavity bags

Client: McConnell DowellProject Dates: 2023-2024 OVERVIEW Design and Construct
QAL waste line, Gladstone – Replacement of crossbeams, installation of pilemedic, installation of scour bags

Client: McConnell DowellProject Dates: July to November 2021 OVERVIEW